Columbia County set the data center rules, then landed Google

The siting standards were adopted before the tenant was named, and the land traded twice on the way there.

Edited by James Rogers · How we report
70 dBCap at the property line
1,900 acReported campus footprint
$78MAuthority land sale, Dec 2025
4-1Vote denying a third site

Columbia County, Georgia adopted its data center zoning district before it had a tenant to name. On July 23, 2026, the Board of Commissioners and the Economic Development Authority of Columbia County announced that Google LLC will be the sole end user and operator of the Columbia County Data Center in Appling, alongside a county, Georgia Power and Google agreement on development standards. The sequence is the story. The rules were written first, and the tenant arrived into them.

Why it matters

This is the template now spreading through data center markets. You sign siting standards with the county up front, and the standards get priced into the land long before you close. Columbia County’s ordinance created a standalone data center district in December and fixed the operating terms instead of leaving them to negotiation: closed loop cooling, no well drilling, a 70 decibel cap on operational equipment at the property line, and utility upgrades paid by the company rather than the county. When commissioners rezoned sites on February 4, 2026, they attached reduced noise limits and wider separation from homes, and they denied a third application, Byrd Farm, by a 4 to 1 vote. Read that vote twice. Standards written in advance are not a formality, and a site that cannot meet them is not a site.

The numbers

The land moved before the name did. The development authority sold the property to Trammell Crow Company for roughly $78 million in December 2025, and Trammell Crow sold it on to Kinetic Infrastructure for close to $500 million, per The Augusta Press. WJBF reported 23 buildings across about 1,900 acres northwest of the White Oak Business Park, and Google committing to cover 100 percent of the project’s energy costs. On the county side, WRDW put the tax ceiling at $166 million a year if two campuses covered the county’s entire share of the property tax bill, roughly 40 percent of the budget. Fire, bond and school levies stay.

What’s next

The approved sites still owe the county site or building plans, a land disturbance application for grading, and a letter from Georgia Power confirming it can serve the load. That will-serve letter is the real schedule gate. Zoning is now the easy part, and power availability sets the clock. More national coverage.