Fort Worth data centers: staff proposes Feb. 23 moratorium vote

Staff asks council for direction. Zoning, noise, water and incentive changes would each still need a council vote.

Last verified · How we report · Report a correction

Feb. 23PROPOSED VOTE
90 daysMORATORIUM LENGTH
19PANEL IDEAS

Fort Worth city staff will give the City Council a timeline for data center rules at its Dec. 1, 2026 work session, which starts at 2 p.m. CT. The informal report (IR 26-0181) proposes a moratorium vote on Feb. 23, 2027. It does not adopt any new rules.

For developers, the key line is in the report itself: state law means neither the moratorium nor future zoning rules would reach projects already in the pipeline.

The news that moved today. Free email. Every weekday morning.

Why it matters

The report counts six pre-development conferences accepted for new data center projects since June 2. That is in addition to five projects inside city limits and two in the extraterritorial jurisdiction that staff listed as under construction or proposed in June.

Rules the council already adopted on Aug. 11 are separate from this proposal. Ordinance 26-28699 requires proof of permits and approvals tied to the Public Utility Commission of Texas and ERCOT before a data center can file for a city development permit. A water policy, M&C 26-0659, requires closed-loop cooling and wastewater pretreatment permits for new data centers in the water utility’s service area.

The numbers

  • Data Center & Infrastructure Commission recommendations presented Nov. 10: 19. Eight continue current practice, five build on staff’s June 2 proposals and six are new.
  • Zoning Commission vote on staff’s June 2 zoning amendments: 7-4 for denial, on July 8.
  • Community survey responses: 1,499 online and 110 at the June 30 open house.
  • Proposed moratorium length: 90 days, requiring a supermajority.

What’s next

The report asks council for direction and proposes these dates, all pending council action:

  • Jan. 5, 2027: staff presentation on all recommendations and implementation options.
  • Jan. 12: second public hearing and first reading of the moratorium ordinance.
  • Feb. 23: second reading and vote. If adopted, the 90-day moratorium would begin.
  • May 18: possible vote on a 90-day extension, which would run to Aug. 22.

Any change to zoning, noise, water or incentives would require a separate council vote. Operators with a project in the city should confirm with staff whether it counts as in the pipeline. More Fort Worth filings are in our Dallas-Fort Worth coverage.

On the record

Informal Report IR 26-0181 lists a proposed Jan. 5, 2027 work session presentation, a Jan. 12 moratorium hearing and first reading, and a Feb. 23 second reading and supermajority vote

Public record · docspublished.io

Primary record

  • Public recordThe report says six data center pre-development conferences were accepted since June 2, on top of five in-city projects and two in the extraterritorial jurisdictionView the record on docspublished.io