No Action is not a denial and not an approval. The calendar shows one vote to close the hearing and none on the merits, leaving the permanent removal, and a 30,781 sq ft Crown Heights assemblage, unresolved.
Last verified · How we report · Report a correction

- Source Briefing
- Public record
- Also reported by The American Developer
The Landmarks Preservation Commission heard the Episcopal Diocese of Long Island’s application to permanently remove a 12-panel Tiffany Studios window from St. Bartholomew’s Church at 1227 Pacific Street on September 15, closed the hearing on a 10 to 0 vote, and then did not vote on the application. The calendar records the disposition on docket LPC-26-12626 in two words: No Action. That is not an approval and it is not a denial. The Diocese asked and did not get an answer.
Why it matters
No Action is a stage, not an ending. LPC’s own description of the Certificate of Appropriateness process says a determination is often made not at the hearing but at a later public meeting, and that a complete application must be ruled on within 90 working days. Here the commission published no reasons, and no decision document exists for a docket it did not decide.
The news that moved today. Free email. Every weekday morning.
The calendar’s bookkeeping shows the difference. On the applications LPC resolved that day it records two votes, one closing the hearing and a second on the merits. On LPC-26-12626 it records one, moved by Commissioner Chen and seconded by Commissioner Ikpemgbe, and nothing after it. The first item on the same calendar shows how the stage ends: 257 Canal Street was approved with modifications 9 to 0, after drawing No Action at its August 4 hearing.
The numbers
We re-pulled PLUTO for Brooklyn Block 1200. Lots 16, 72 and 80, all held by the Diocese’s trustees, total 30,781 sq ft of land carrying 27,036 sq ft of building, a blended built FAR of 0.88. At each lot’s own maximum residential FAR, 7.52 on the church lot and 3.0 on the two R6A lots, the site supports about 196,000 sq ft, leaving roughly 169,000 sq ft unbuilt. One discrepancy: PLUTO records Lot 16 as C6-3A, the LPC calendar as C6-3.
What’s next
LPC has posted its September 29 agenda and LPC-26-12626 is not on it. The buildings department record has not moved: still no demolition or new-building application. The window is already out of the church, crated and in storage in Queens under the temporary approval we reported Monday.
What a developer underwriting this assemblage learned on Tuesday is about the schedule. The 169,000 sq ft of unused floor area is still there and the marketing is still running, but the window question cannot be closed out until the commission rules, and there is no date and no reasoning to price against. Church-owned land is one of the few large soft sites left in central Brooklyn, and this is its cost: the path runs through a body that can decline to answer. See the New York market.
Quick answers
- What is the latest on 1227 Pacific Street?
- The commission closed the hearing on the Diocese of Long Island's window removal 10 to 0, then recorded no vote on the application itself.
- Who is developing 1227 Pacific Street?
- Episcopal Diocese of Long Island and Ariel Property Advisors, according to NYC Landmarks Preservation Commission, public hearing and meeting calendar, September 15, 2026.
- What are the key numbers for 1227 Pacific Street?
- Vote to close the hearing: 10-0-0; Disposition on LPC-26-12626: No Action; Unbuilt floor area, our calculation: 169,000 sq ft; LPC ruling clock, once complete: 90 working days.
On the record
On the September 15 applications LPC decided, the calendar records two votes, one closing the hearing and a second on the merits. On LPC-26-12626 it records one, moved by Commissioner Chen and seconded by Commissioner Ikpemgbe, 10-0-0, with the disposition entered as No Action and no merits vote after it.
Public record · nyc.gov
Primary record
- Public recordLPC has published its September 29 public hearing and meeting agenda and docket LPC-26-12626 does not appear on it, so the application is not re-calendared for the commission's next session.View the record on nyc.gov
- Public recordWe re-pulled PLUTO for Brooklyn Block 1200: Lots 16, 72 and 80 total 30,781 sq ft of land carrying 27,036 sq ft of building, a blended built FAR of 0.88, leaving roughly 169,000 sq ft of unbuilt floor area. PLUTO records Lot 16 as C6-3A with an R6A overlay, where the LPC calendar lists the zoning as R6A and C6-3.View the record on data.cityofnewyork.us
- Our coverageWe reported on September 15 that the 12 panels were already out of the church, crated by J&R Lamb Studios and stored in Queens under temporary approval PMW-25-01633, and that Ariel Property Advisors was marketing the site as a 30,781 sq ft assemblage.Read our earlier story
- NYC Landmarks Preservation Commission, Certificate of Appropriateness processA determination is often not made until a subsequent public meeting; a complete application must be ruled on within 90 working days
Also reported by
- The American DeveloperTiffany window leaves a Brooklyn landmark as its site hits the market