Plano Texas Oncology center: state lists $45M, firm says $120M

Two public figures for the same Collin County building do not match, and neither explains the gap.

Verified . Report a correction

Last verified · How we report · Report a correction

$45Mstate-registered cost
$120Mcompany-cited cost
96,000filed sq ft

The Plano cancer center that Texas Oncology says will replace four of its existing locations carries two very different price tags in the public record. A state accessibility registration for the building at 5100 Village Creek Dr lists an estimated cost of $45 million. The company has described the project as a $120 million center.

Why it matters

The state filing is the only record we found that ties a dollar figure, a square footage and a schedule to the address. It describes a 96,000 sq ft new building registered on April 29, 2025, privately funded, with construction starting June 3, 2025 and completion on Nov. 20, 2026. At $45 million, that is about $469 per sq ft for the building as registered.

The permits and deals moving Miami.
Free, every weekday.

Edition: All markets.

Texas Oncology’s June 2025 groundbreaking announcement uses $120 million, and trade coverage of the event describes a three-story building of roughly 100,000 sq ft with an opening expected in December 2026. At $120 million, the filed 96,000 sq ft would be about $1,250 per sq ft. The public documents do not say what the larger number includes, so we do not treat either figure as the full cost of the project.

For anyone tracking healthcare real estate in Collin County, the gap is the useful detail. Medical office registrations often capture only the building scope, while an operator’s headline number can bundle equipment, fit-out and other items. That is a general pattern, not something either document states about this project.

The numbers

  • Filing: TABS2025017756, CWD Plano Medical Office Building, facility name Texas Oncology Plano Cancer Center.
  • Address: 5100 Village Creek Dr, Plano, TX 75093.
  • State-registered cost: $45,000,000, new construction, privately funded.
  • Size on the filing: 96,000 sq ft. Company-cited size: about 100,000 sq ft over three floors.
  • Schedule on the filing: start June 3, 2025, completion Nov. 20, 2026.
  • Owner of record: CWD Plano LLC. Design firm: RS&H. The filing lists no contractor.
  • Company-cited cost: $120 million; four existing Texas Oncology locations consolidating into the site.

The owner of record is a property-level entity, so we name the operator, Texas Oncology, in the headline and developer field. Trade coverage lists Cottonwood Development Partners and McCarthy Building Companies on the project team, but it does not state their roles, and we do not assign them one.

What’s next

We found no record confirming the center has opened. The filed completion date is Nov. 20, and the company’s stated target is December, so the next markers are a certificate of occupancy from the City of Plano and the company’s own opening notice. We will update this story if either appears.

For more Dallas-Fort Worth development filings, see our Dallas market page.

Source: Texas Department of Licensing and Regulation, TABS; Texas Oncology.

Quick answers (3)

Quick answers

What is the latest on Texas Oncology Plano Cancer Center?
A state filing for the Plano cancer center at 5100 Village Creek Dr lists $45M and a Nov. 20 completion. Texas Oncology cites $120M and a December opening.
What are the key numbers for Texas Oncology Plano Cancer Center?
state-registered cost: $45M; company-cited cost: $120M; filed sq ft: 96,000; filed completion date: Nov. 20, 2026.
Where does the information on Texas Oncology Plano Cancer Center come from?
The story cites Texas Department of Licensing and Regulation (TABS), Texas Oncology and Medical Construction & Design.
Sources and records (3)

On the record

TABS project TABS2025017756, registered April 29, 2025, lists the Texas Oncology Plano Cancer Center at 5100 Village Creek Dr, Plano (Collin County) as a $45,000,000, 96,000 sq ft new building, privately funded, with a June 3, 2025 start and Nov. 20, 2026 completion, owner CWD Plano LLC, design firm RS&H.

Public record · tdlr.texas.gov

How we report →

Next story · DallasOld Parkland East Phase 2: $325M Dallas office project registeredRead next →A Nov. 24 state filing lists a $325 million, 290,000 sq ft office project at 3910 Maple Ave in Dallas, with construction set to start March 1, 2027.
Topics, people and developers
Newsletter

Get the Dallas Daily Index

One free briefing every weekday morning.

Edition: All markets.