PROJECT · NATIONAL / 2 UPDATES

Project Camellia

The development timeline, every story tracking Project Camellia, oldest first.

  1. Jul 23, 2026
    Development
    OpenAI commits $20B to first self-built data center near Savannah

    OpenAI will design and build its own 3.2-gigawatt campus in Effingham County, its first, committing $20B to unlock local incentives on the Georgia coast.

  2. Aug 17, 2026
    Policy & Planning
    Georgia PSC Extends Review of Georgia Power's OpenAI Contract

    Georgia's PSC pushed its deadline on Georgia Power's 3.2 GW OpenAI contract to Aug. 26, the regulatory step now gating Project Camellia's power.

More National development ↗