$54.3M foundation permit issued for Potranco data center

A $54.3M foundation permit at 1535 NW Crossroads pairs with two state filings totaling $75M for a single-tenant data center on San Antonio's far west side.

Last verified · How we report · Report a correction

$54.3Mpermit valuation
208,137 sq ftpermitted area
$75MTABS estimates

A foundation permit for a data center at 1535 NW Crossroads on San Antonio’s far west side was issued on Nov. 12, 2026, with a declared valuation of $54.3 million. Two filings with the Texas Department of Licensing and Regulation tie the project to COPT, which is listed as the owner and which calls the project COPT Potranco.

The City of San Antonio permit, number COM-FND-PMT26-40300012, is a commercial foundation permit for new work. The city’s open data record lists 208,137 sq ft and places the address in Council District 6. A declared valuation is the job value stated on the application. It is not a purchase price and not a loan amount.

The permits and deals moving Dallas. Free, every weekday.

The state filings add detail the permit does not. TABS2026014988, titled COPT Potranco - Core Shell, lists COPT SAN ANTONIO LP as owner and Gensler as the design firm. It carries an estimated cost of $25 million and describes a two-story core and shell for a future single-tenant computer data center. Its estimated start is Oct. 1, 2026 and its estimated completion is Nov. 30, 2027.

A second registration, TABS2026017435, titled COPT Potranco - TI, covers the tenant finish-out for the same kind of single-tenant data center. It lists the same owner and design firm, an estimated cost of $50 million, a start of Nov. 4, 2027 and a completion of Sept. 21, 2029.

The records do not name the future tenant. We have not attributed the project to any operator, because nothing in the permit or the TABS filings does.

Why it matters

A two-phase filing like this one shows the build order the owner has registered with the state: the shell first, then the tenant fit-out about a year later. For contractors and suppliers, the permit and the TABS dates mark when work is expected to open up. The records do not say what the finished building will draw in power or jobs, so we are not estimating either.

More San Antonio filings are tracked on our San Antonio market page.

The numbers

  • $54.3 million: declared valuation on the Nov. 12, 2026 foundation permit.
  • 208,137 sq ft: area on the permit.
  • $25 million: estimated cost of the core and shell, TABS2026014988.
  • $50 million: estimated cost of the tenant improvement, TABS2026017435.
  • $75 million: the two TABS estimates combined.

The permit value and the TABS estimates are separate records with different purposes, and we have not reconciled them. The permit area (208,137 sq ft) is also larger than the two TABS filings, which list 141,979 sq ft and 141,081 sq ft.

What’s next

The core and shell registration lists a completion date of Nov. 30, 2027, and the tenant improvement is registered to start in November 2027. Further permits for the building itself, and any utility filings, would show how the project moves from foundation to shell. We will update if those filings appear.

Quick answers

What is the latest on COPT in San Antonio?
A $54.3M foundation permit at 1535 NW Crossroads pairs with two state filings totaling $75M for a single-tenant data center on San Antonio's far west side.
What are the key numbers for COPT?
permit valuation: $54.3M; permitted area: 208,137 sq ft; TABS estimates: $75M.
Where does the information on COPT come from?
The story cites City of San Antonio open data and Texas Department of Licensing and Regulation.

On the record

Permit COM-FND-PMT26-40300012, issued 2026-11-12, declared valuation $54,300,000, 208,137 sq ft, 1535 NW Crossroads

Permit · data.sanantonio.gov

Primary record

How we report →