Downtown Miami $129M tower permit issues after 1,024 days in review
Miami issued a $128.7M permit for 569,969 sq ft at 50 NE 3rd St, built by John Moriarty & Associates, after 1,024 days in plan review.
Last verified · How we report · Report a correction

- Source Briefing
- Public record
- Also reported by Florida YIMBY
The City of Miami issued a new-construction permit on September 28 for 50 NE 3rd St in downtown Miami, valued at $128,663,319 and covering 569,969 square feet. The contractor is John Moriarty & Associates of Florida. The record’s own review clock shows the plans sat in city review for 1,024 days, nearly three years.
Why it matters
Plans for the site were submitted on December 1, 2023, and accepted on December 8, 2023, according to the city record. Issuance came on September 28, 2026. For builders and subcontractors, that is the real schedule risk on a large downtown job: the gap before the permit, not the build after it.
The permits and deals moving Miami. Free, every weekday.
The permit lists the work as multifamily rental with retail, professional office and a multi-floor parking garage. It was handled through a private provider, and the permit is active and ready for inspections. The wire row lists no owner. Florida YIMBY reported in November 2025 that Namdar Group was advancing a two-tower project at 50 NE 3rd Street. We could not confirm from the permit that this approval covers that project or one of its phases.
The numbers
- Valuation: $128,663,319, about $226 per square foot
- Size: 569,969 square feet, zoned T6-80-O under Miami 21
- Plan review: 1,024 days, December 2023 to September 2026
- Contractor: John Moriarty & Associates of Florida, based in Hollywood
What’s next
With the permit active, the next public milestones are inspections and a certificate of occupancy, which the record lists as required. Trades bidding on this scope should expect mobilization soon, though no start date appears in the record.
Developers weighing downtown sites should price the review lag into carry costs. Track more projects on the South Florida market page.
More in Foreclosure & Distress News. See the upcoming commercial foreclosure auctions. Every South Florida foreclosure case, with the debt and the case file, is on the Deal Board.
Quick answers
- What is the latest on 50 NE 3rd St?
- Miami issued a $128.7M permit for 569,969 sq ft at 50 NE 3rd St, built by John Moriarty & Associates, after 1,024 days in plan review.
- Who is developing 50 NE 3rd St?
- John Moriarty & Associates, according to City of Miami Building Department.
- What are the key numbers for 50 NE 3rd St?
- permit valuation: $128.7M; new construction: 569,969 sq ft; in plan review: 1,024 days.
On the record
Permit BD23028187001B001 was issued 2026-09-28 after 1,024 days in plan review, from a December 2023 plan submission, for $128,663,319 of new construction
Permit · miami.gov
Also reported by