Menlo Park, N17 Willow Road 665-unit case set for court Dec. 14

N17's writ petition over 80 Willow Road, a 665-unit mixed-use plan in Menlo Park, is set for a Dec. 14 hearing, with a decision expected in January 2027.

Last verified · How we report · Report a correction

665units
458 fttallest tower
Dec. 14court hearing

A San Mateo County Superior Court hearing on Dec. 14 will test whether Menlo Park must process N17 Development’s 80 Willow Road plan under California’s AB 2011 fast-track law. The city’s project page says a decision is expected in mid to late January 2027.

Why it matters

For operators, the ruling would signal whether AB 2011 can force a ministerial path past a city that says a site is ineligible, which bears on the hotel, office and housing mix at stake here.

The news that moved today. Free email. Every weekday morning.

N17, acting through Willow Park LLC, filed a writ petition on Oct. 2, 2026 (case 26-CIV-07675). The petition alleges the city did not process the project under AB 2011 and denied it Builder’s Remedy protections, according to the city’s page. The applicant pursues the project under SB 330, the Builder’s Remedy and AB 2011.

The city says it determined on May 6, 2026 that the application remains ineligible for AB 2011 processing. It also says the state Attorney General’s office sent a July 29 notice under AB 712 claiming the city violated AB 2011 and the Housing Accountability Act. The city responded on Oct. 1 that it complies with state law. Its page says the council was told in a Sept. 29 closed session that the Attorney General concluded the project is consistent with AB 2011, and that the city disagrees.

AB 2011 projects are exempt from CEQA, so the eligibility question decides which review path applies.

The numbers

The 6.7-acre site sits in the Linfield Oaks neighborhood and is the former Sunset Magazine headquarters. The city lists about 665 residential units, 332,000 square feet of office, 17,000 square feet of retail and a 130-room hotel of 164,000 square feet. Three buildings would range from 301 to 458 feet tall, and a preschool of about 3,000 square feet is included.

The city page also records a Nov. 12 Government Code claim from Willow Project, LLC alleging delay damages tied to the city not approving the project ministerially. The city contests it. San Francisco readers can compare this with the Tarlton and 1005 O’Brien final EIR also moving in Menlo Park.

What’s next

Per the filings schedule, which the city notes is subject to change, N17 filed its opening brief Nov. 18. The city’s opposition is due Dec. 1 and the reply Dec. 8, ahead of the Dec. 14 hearing. No ruling exists yet, and the outcome is pending.

The city says it is still processing the application as filed, and the applicant has not yet submitted the funds needed to begin CEQA work. An April 13, 2026 consistency review found the application inconsistent with multiple development standards.

Quick answers

What is the latest on 80 Willow Road (Willow Park)?
N17's writ petition over 80 Willow Road, a 665-unit mixed-use plan in Menlo Park, is set for a Dec. 14 hearing, with a decision expected in January 2027.
Who is developing 80 Willow Road (Willow Park)?
N17 Development, according to City of Menlo Park.
What are the key numbers for 80 Willow Road (Willow Park)?
units: 665; tallest tower: 458 ft; court hearing: Dec. 14.

On the record

The city's project page lists a Dec. 14 hearing in case 26-CIV-07675, with the city's opposition brief due Dec. 1 and N17's reply due Dec. 8.

Public record · menlopark.gov

How we report →

Next story · San FranciscoOakland Proposes Oakport Field License to Oakland UnitedOakland's council is set to consider on Dec 1 a proposed 15-year Oakport Field license at $500 a month plus 15% of net sponsorship revenue.
Newsletter

Get the San Francisco Daily Index

One free briefing every weekday morning.