Miami Beach Reviews Stalled Five Park Pedestrian Bridge

Miami Beach commissioners ordered a feasibility review of the Five Park pedestrian bridge after Terra and GFO Investments missed the deadline set at approval.

Edited by Hannah Joseph · How we report
$12.5MTotal budget for the pedestrian bridge
$9.61MCity of Miami Beach's share of the cost
Feb. 2025Groundbreaking on the bridge
Oct. 2026City review results due

Miami Beach commissioners have ordered an independent engineering review of the Fifth Street pedestrian bridge that Terra and GFO Investments agreed to help deliver as a public-benefit condition of their Five Park tower approval, after the project stalled more than a year past its groundbreaking.

Why it matters

The bridge was written into the development agreement that allowed Terra and GFO Investments to build the 48-story Five Park condo tower at 500 Alton Road, one of the public benefits the city extracted in exchange for approving the project’s height and scale. Miami Beach is now enforcing that commitment after construction stalled, a reminder to developers working in the South Florida market that public-benefit obligations attached at entitlement do not end when the certificate of occupancy is issued. A developer pricing a bridge, park, or streetscape concession into a project’s approval needs to account for engineering risk the city may later hold them to, not just the headline dollar figure.

The numbers

The bridge, designed by artist Daniel Buren to carry pedestrians over the MacArthur Causeway at Fifth Street and connect the South of Fifth and West Avenue areas to the Baywalk near Five Park, carries a $12.5 million budget. The city has committed up to $9.61 million of that, with Terra and GFO Investments obligated for roughly $2.85 million. Officials broke ground in February 2025. Underground high-voltage Florida Power & Light feeder lines beneath Fifth Street and West Avenue have since created construction conflicts, with commissioners saying FPL gave conflicting line locations and crews struck a line encasement while drilling. The city’s administrative review of the bridge’s feasibility is due back in October 2026.

What’s next

Commissioner Alex Fernandez said at the meeting, “The voters were promised a bridge. They’ve been waiting for a long time.” If the engineering review finds the bridge cannot be completed as designed, the city has said it would negotiate an alternative, an over-water Baywalk connection, in its place. The October report will determine whether Miami Beach continues pursuing the bridge as approved or moves to renegotiate the public-benefit terms tied to the Five Park entitlement.