TeraWulf Clears Power Hurdle for Anthropic Data Center in Kentucky
The state's grid already had the interconnection built. That is the whole pitch.
Last verified · How we report · Report a correction

- Source Briefing
- Company announcement
- Also reported by Construction Dive
Kentucky’s Public Service Commission approved a 482-megawatt electric service agreement for TeraWulf’s data center campus on the former Century Aluminum smelter site in Hawesville, clearing the last major regulatory hurdle for a project anchored by a 20-year lease with Anthropic, according to TeraWulf’s own announcement.
Why it matters
The smelter closed and left behind exactly what data center developers are fighting utilities and years-long interconnection queues to get: a grid connection already built for heavy industrial load. TeraWulf is developing the site, branded the Justified Data Campus, for an estimated $4.0 billion to $4.5 billion in site work and initial data halls, work that Fluor is now handling master planning and preconstruction on. Anthropic has leased approximately 401 megawatts of critical IT capacity there under a 20-year deal worth roughly $19 billion in contracted revenue over its initial term. CEO Paul Prager explained the site-selection logic: power limits AI infrastructure, and how that power reaches the market matters.
The permits and deals moving the US. Free, every weekday.
The numbers
The Kentucky PSC’s retail electric service agreement covers up to 482 megawatts in Hancock County, the transmission capacity that survived the smelter’s shutdown. TeraWulf estimates development costs between about $10 million and $12 million for each megawatt across the site buildout. The first of Anthropic’s capacity should come online by late 2027, ramping to the full 401 megawatts by early 2028.
What’s next
TeraWulf and Fluor now move from preconstruction into full site work under the approved power agreement. The contrast with this month’s data center news elsewhere is stark. While Hancock County, Kentucky welcomed the load with a shuttered smelter’s grid already in place, Palm Beach County voted a year-long application freeze and Miami-Dade staff moved to write data centers out of a new industrial zoning category entirely. The sites winning approval fastest now share one trait: dead industrial land that already comes wired for the load nobody wants living next door.
Quick answers
- Did TeraWulf clear Power Hurdle for Anthropic Data Center in Kentucky?
- Kentucky regulators approved a 482MW power deal for TeraWulf's Anthropic-leased data campus on a former Century Aluminum smelter site.
- Who is developing Justified Data Campus?
- TeraWulf and Anthropic, according to TeraWulf Inc.
- What are the key numbers for Justified Data Campus?
- Power approved: 482MW; Leased to Anthropic: 401MW; Site investment: $4-4.5B; Phase 1 online: H2 2027.
On the record
Two South Florida jurisdictions have moved to bar or freeze data centers in the same month Kentucky regulators cleared TeraWulf's power deal: Miami-Dade staff drafted a category-level exclusion in July and Palm Beach County's Zoning Commission voted a year-long freeze on Aug. 6, a pattern visible across our own coverage.