TeraWulf's Lake Mariner Data Center Pushes CB-5 to 2027
TeraWulf's Q3 report shows 102 MW live at its Lake Mariner data center in Niagara County and 336 MW under construction, with CB-5 now slated for early 2027.
Last verified · How we report · Report a correction

TeraWulf’s Lake Mariner campus for AI computing in Niagara County, New York, had 102 megawatts of critical IT capacity earning rent at the end of September, and another 336 megawatts under construction, according to the company’s third-quarter 2026 results released November 6. CB-5, the larger of the two buildings, has slipped into the first part of 2027.
Why it matters
For anyone tracking power-heavy projects in upstate New York, this is the clearest public read on how much of Lake Mariner is actually generating revenue. When we covered the campus in September, the filing trail pointed to the 160 MW CB-5 building opening in the back half of this year, per TeraWulf’s 2025 lease announcement. The Q3 release moves that building into early 2027. CB-4, the other building, should start delivering in phases and collecting rent in the fourth quarter.
The permits and deals moving New York. Free, every weekday.
The timing sits inside a state debate over large data centers. Governor Hochul announced a one-year pause on new hyperscale projects in July. The Q3 release does not address whether that pause touches this campus.
The numbers
TeraWulf reported total third-quarter revenue of $76.2 million, up from $50.6 million a year earlier. High-performance computing lease revenue was $63.0 million, about 83 percent of the total, while digital asset revenue fell to $13.2 million from $43.4 million. The company says Lake Mariner construction is landing between $8 million and $10 million for every megawatt of IT load, the budget the company set. Across that range, 336 MW under construction implies roughly $2.7 billion to $3.4 billion of build cost, our arithmetic and not a company figure.
CFO Patrick Fleury said Lake Mariner is “progressing within cost guidance.” At quarter-end TeraWulf held about $2.4 billion in cash and restricted cash, and after the quarter its revolver was upsized: commitments went up by $150 million to a total of $400 million. The release does not attach financing to Lake Mariner specifically.
What’s next
Rent from CB-4 is expected to begin in the fourth quarter, which is the first test of whether the company’s schedule holds. CB-5 is the second test. The release does not name the Lake Mariner tenants, though the earlier SEC announcement of the CB-5 lease identified Fluidstack. TeraWulf also said it is pursuing additional campuses in New York and Maryland, without naming sites. Separately, Niagara County has hired counsel to review whether the campus owes sales tax, a matter covered in our September report on the ground lease structure at Lake Mariner.
Quick answers
- What is the latest on Lake Mariner?
- TeraWulf's Q3 report shows 102 MW live at its Lake Mariner data center in Niagara County and 336 MW under construction, with CB-5 now slated for early 2027.
- Who is developing Lake Mariner?
- TeraWulf and Fluidstack, according to TeraWulf Inc. (company release).
- What are the key numbers for Lake Mariner?
- revenue-generating at Lake Mariner (Sept 30): 102 MW; under construction (CB-4 and CB-5): 336 MW; cost guidance per critical IT MW: $8M-$10M.
On the record
TeraWulf's Q3 2026 release reports 102 MW of revenue-generating critical IT capacity at Lake Mariner as of September 30, 2026, with 336 MW under construction across CB-4 and CB-5; TeraWulf's 2025 CB-5 lease announcement pointed to operations beginning in late 2026, and the company now now says early 2027.
Public record · financialcontent.com
Primary record
- SEC EDGAR / TeraWulf Inc.TeraWulf Announces Fluidstack Expansion with 160 MW CB-5 Lease at Lake Mariner
Also reported by
- TeraWulf Inc. (company release)TeraWulf Reports Third Quarter 2026 Results
- The BlockTeraWulf's bitcoin mining revenue falls 69% as HPC leasing surges