Methodist registers $56M, 7-story garage at 7700 Floyd Curl Dr.
The TABS filing sets a Jan. 4, 2027 start and a Jan. 8, 2029 finish for a 7-story structure tied into the existing hospital.

- Source Briefing
- Public record
Methodist Healthcare System of San Antonio registered a $56 million parking garage and ancillary services project at Methodist Hospital, 7700 Floyd Curl Dr., with the Texas Department of Licensing and Regulation on Nov. 11, 2026. The filing, TABS2027005700, describes a 7-story, 440,000 sq ft structure that connects to the existing hospital at level 1 and to the existing Parking Garage 3 at level 3.
Why it matters
The money goes to parking and support space rather than patient beds. The filing includes a sub-level used mainly for storage by Materials Management, so the structure carries supply-chain space as well as cars. Perkins and Will is listed as the design firm. No general contractor appears in the registration, so the construction bid is still ahead of the Jan. 4, 2027 start date.
The news that moved today. Free email. Every weekday morning.
The numbers
TDLR records an estimated cost of $56,000,000 for 440,000 sq ft of new construction, about $127 per sq ft. The schedule runs from Jan. 4, 2027 to Jan. 8, 2029, roughly 24 months. The state lists the project as privately funded, on private land, for private use. The owner of record is Methodist Healthcare System of San Antonio, LTD., with a mailing address in Indianapolis. The status is “Project Registered.”
What’s next
A City of San Antonio building permit would be the next public record to show the project moving, and it would likely name a contractor. After completion, the owner must request a Registered Accessibility Specialist inspection under TDLR rules. This is a separate project from the surgery center the system registered earlier in the fall; see our report on the Saga Metro ASC filing, and for more activity across the metro, see the San Antonio market hub.
Quick answers
- What is the latest on Methodist Hospital Parking Garage & Ancillary Services?
- Methodist Healthcare System of San Antonio registered a $56 million, 440,000 sq ft parking garage at Methodist Hospital with TDLR on Nov. 11, 2026.
- What are the key numbers for Methodist Hospital Parking Garage & Ancillary Services?
- estimated cost: $56M; garage area: 440,000 sq ft; stories: 7.
- Where does the information on Methodist Hospital Parking Garage & Ancillary Services come from?
- The story cites Texas Department of Licensing and Regulation, TABS2027005700.
On the record
TABS2027005700, registered Nov. 11, 2026, lists a 7-story, 440,000 sq ft parking garage at 7700 Floyd Curl Dr. with an estimated cost of $56,000,000, a Jan. 4, 2027 start and a Jan. 8, 2029 completion.
Public record · tdlr.texas.gov