Six items clear South Florida agendas this week and next with real scope and real dollars attached, from a $399 million funding jump on Fort Lauderdale-Hollywood International Airport’s Terminal 5 to four Pompano Beach CRA and site-plan actions. Three are contracts a GC already won and now needs subs for. Three are projects still short a general contractor.
Why it matters
A contract award tells a sub who is mobilizing now. An approvals hearing tells a GC a job is not staffed yet and worth a call. Both showed up this week. Broward’s Sept. 22 agenda has the Aviation Department awarding three civil contracts at FLL and HWO totaling $42.8 million, plus a near-doubling of the funding cap on JetBlue’s Terminal 5 deal. Pompano Beach’s CRA and Development Review Committee, both meeting this week, carry four items ranging from a stalled townhome project restarting under a hard 2027 deadline to two buildouts still needing contractors.
The numbers
- FLL: Central Civil Construction Co. awarded $20,338,728 for Taxilane ADG III Westside (Taxilane D), Bid No. PNC2131441C1. Broward County Commission, Sept. 22.
- FLL and HWO: FG Construction LLC awarded an open-end Annual Civil Repairs and Maintenance contract, $12,181,900 in year one and up to $36,545,700 over three years, Bid No. PNC2131233B1. Broward County Commission, Sept. 22.
- FLL: Ranger Construction Industries Inc. awarded $10,288,888 for Taxilane T Rehabilitation, Bid No. PNC2132049C1. Broward County Commission, Sept. 22.
- FLL: JetBlue’s Terminal 5 construction management deal grows $398,954,000 to a new $802,394,000 not-to-exceed total, completion due within 1,277 days of the third Notice to Proceed. Broward County Commission, Sept. 22.
- Pompano Beach: Solstice Townhomes LLC, land on North Dixie Highway between NW 15th Court and NW 15th Place, construction 90 percent complete, disposition agreement reinstated with a completion deadline of June 30, 2027. CRA board, Sept. 15.
- Pompano Beach: SL 1241-1251 N Dixie LLC and Old Town Center LLC, two CRA grants covering roughly $565,000 combined in renovation work (windows, signage, parking, plumbing, electrical, framing) at 1241-1251 N Dixie Highway and 120-122 N Flagler Avenue. CRA board, Sept. 15.
- Pompano Beach: a minor site plan for a multifamily project at 3214 SE 11th Street, owner SE 11th Street Pompano PJ LLC, zoned RM-20. Development Review Committee, Sept. 16.
What’s next
Subs chasing FLL work should register with Central Civil, FG Construction and Ranger now, before mobilization fills. The Terminal 5 jump signals more packages coming regardless of who holds the prime. In Pompano Beach, Solstice Townhomes’ 2027 deadline is a closeout window for finish trades, and the two CRA buildouts move to construction once grants execute. Our South Florida approvals tracking updates as each board acts.
Sources
- Broward County LegistarCounty Commission Regular Meeting Agenda, September 22, 2026
- City of Pompano Beach LegistarCommunity Redevelopment Agency Agenda, September 15, 2026
- City of Pompano Beach LegistarDevelopment Review Committee Agenda, September 16, 2026